Ealing Common Piling Works
A planned two level piled basement immediately adjacent to
operational Ealing Common Station required the design of a
multi-tier piling working platform and associated plant access
ramps. With piling cut off level 3m above the adjacent Ealing
Common platforms, Deltaline designed the working platform and
retaining structure capable of supporting piling rig
operations within 3m horizontal metres of the station wall.
All piles were installed without complication.
In addition Deltaliine provided designs for site small
power/lighting and all perimeter hoardings.
To temporarily divert dirty water Deltaline also conceived
and provided civil and electrical designs to facilitate
installation of a waste water pump system.
Deltaline provided a fully qualified Temporary Works
Coordinator to guide, monitor , record and approve site
operations.